During the application of the screed, the trapezoid perforated anchoring leg of Schlüter-BARA-RK is solidly embedded into the mortar bed while the upper edge of the profile is used to screed the mortar bed to the appropriate height. Schlüter-TROBA-PLUS, serving as sub-surface drainage, shall be laid between the waterproofing layer and the screed in order to prevent penetrating water from collecting in the screed layer.
If Schlüter-DITRA is to be installed, the screed is levelled 3 mm below the top of the profile. DITRA uncouples the tile covering from the screed and neutralises stresses caused by differential movement, primarily due to temperature fluctuations, between the screed and the tile. In addition, DITRA in conjunction with the tile covering creates a bonded surface-waterproof layer.